基于RFID的特高壓變電站主設(shè)備智慧管控平臺(tái)應(yīng)用研究
肖峰1,付寶良1,潘宏承1,李盈盈1,劉振1,朱王偉1,林松2,張東旭1,江海濤1
(1 國(guó)家電網(wǎng)有限公司特高壓建設(shè)分公司,北京 100053;
2 北京洛斯達(dá)科技發(fā)展有限公司,北京 100120)
摘 要:在特高壓變電站的建設(shè)過(guò)程中,缺少一個(gè)從計(jì)劃、生產(chǎn)、運(yùn)輸、安裝、運(yùn)維等全過(guò)程的主設(shè)備管理平臺(tái),無(wú)法對(duì)主設(shè)備各個(gè)階段進(jìn)行有效管理。構(gòu)建了一種特高壓變電站主設(shè)備全過(guò)程智慧管控平臺(tái),介紹了該平臺(tái)的系統(tǒng)目標(biāo),給出了系統(tǒng)架構(gòu)及技術(shù)框架,對(duì)無(wú)線(xiàn)射頻技術(shù)、二維碼掃描技術(shù)等關(guān)鍵技術(shù)進(jìn)行了闡述,經(jīng)工程應(yīng)用表明,該平臺(tái)實(shí)現(xiàn)了主設(shè)備及關(guān)鍵組成部分的生產(chǎn)制造、運(yùn)輸、現(xiàn)場(chǎng)安裝、試驗(yàn)調(diào)試全過(guò)程質(zhì)量環(huán)節(jié)管控,滿(mǎn)足質(zhì)量控制要點(diǎn)、全過(guò)程追溯要求。
關(guān)鍵詞:物聯(lián)網(wǎng);主設(shè)備;智慧管控;特高壓
中圖分類(lèi)號(hào):TM73 文獻(xiàn)標(biāo)識(shí)碼:B 文章編號(hào):1007-3175(2022)03-0063-04
Application Research on the Whole Process Intelligent Management and
Control Platform of UHV Substation Main Equipment Based on RFID
XIAO Feng1, FU Bao-liang1, PAN Hong-cheng1, LI Ying-ying1, LIU Zhen1, ZHU Wang-wei1, LIN Song2, ZHANG Dong-xu1, JIANG Hai-tao1
(1 State Grid Corporation of China UHV Construction Branch, Beijing 100053, China;
2 Beijing North-Star Technology Development Co., Ltd, Beijing 100120, China)
Abstract: It is impossible to effectively manage all stages of the fundamental equipment due to the lack of a capital equipment management platform covering the whole process of planning, production, transportation, installation, operation, and maintenance during the construction of UHV substations.This paper constructed a whole-process intelligent management and control platform for the central equipment of UHV substations and introduced the system goals of the platform. It also provided the architectural and technical framework of the system and elaborated the key technologies such as wireless radio frequency technology and two-dimensional code scanning technology.The engineering application results showed that the platform could realize the quality control of the whole process of manufacturing, transportation,on-site installation, testing, and debugging of the main equipment and the crucial components. It meets the requirements of quality control points and the whole process traceability.
Key words: Internet of Things; main equipment; smart control; UHV
參考文獻(xiàn)
[1] 郭京誼. 特高壓變電站主設(shè)備安裝質(zhì)量管理探究[J]. 工程建設(shè)與設(shè)計(jì),2019(20) :52-53.
[2] 張勇生. 基于電力物聯(lián)網(wǎng)的特高壓變電站機(jī)房智慧監(jiān)控研究[J]. 信息技術(shù)與信息化,2020(10) :236-238.
[3] 王雍會(huì). 特高壓變電站運(yùn)維精益化管理探討[J] .中國(guó)外資,2019(22) :72-73.
[4] 張人英,張敏,孫露潔. 特高壓變電站 1 000 kV GIS 安裝質(zhì)量控制探討[J]. 科技與創(chuàng)新,2017(19) :124-125.
[5] 牛凱,肖鋒,洪芳華,江辰,張飛龍. 基于物聯(lián)網(wǎng)技術(shù)的電力重點(diǎn)物資運(yùn)輸監(jiān)控應(yīng)用研究[J] . 物流工程與管理,2018,40(7) :91-93.
[6] 江海濤,崔艷軍,張爾樂(lè),周萬(wàn)駿,葉松,蔡劉露,彭旺,杜亞星. 物聯(lián)網(wǎng)技術(shù)在特高壓主設(shè)備智慧管控平臺(tái)中的應(yīng)用[J]. 電工電氣,2021(12) :60-64.